Progress update on 112 Cashel Street

Works are progressing on the central city site at 112 Cashel Street.

Contractors have finished installing over 106 600mm diameter helix steel screw piles to a depth of approximately 5-6 metres.

Perimeter foundation beams have been completed, with final steel being placed to the internal foundation beams and concrete being poured.  Ground beams vary in depth from 700mm to 1500mm.

 

 